Material: carbon steel plastic spraying
Size: (L)0.96m×(B)0.71m×(H)0.42m (size ±0.1m).
Configuration instructions are as follows:
Main air switch: as the main power control device of the cabinet, it is an essential component of all kinds of control cabinets.
PLC: Selection should be based on project scale and demand. If the project scale is small, integrated PLC; can be selected; If the project scale is large, it is necessary to adopt modular card-type PLC, and it may be necessary to configure redundant systems (that is, two sets of equipment run alternately).
24VDC switching power supply: Most PLCs have their own 24VDC power supply, and the configuration of this switching power supply needs to be determined according to actual needs.
Relay: PLC can usually send instructions directly to the control loop, but it needs to be relayed through the relay in certain scenarios. For example, if the output port of PLC is a live signal of 24VDC, and the design of control loop requires PLC to provide a node of 220VAC, it is necessary to configure a relay at the output port of PLC-the relay acts when the command is issued, and the node of control loop is connected to the normally open or normally closed contact of the relay. The configuration of relay should be determined according to the actual working conditions.
Wiring terminal: it is an essential component of all kinds of control cabinets, and its configuration quantity needs to be determined according to the number of signals.
The above is the basic configuration of the standard PLC control cabinet. If the control cabinet needs to realize additional functions, additional components are required. For example, if it is necessary to supply power to field instruments or small control boxes, the number of air switches should be increased; If it is necessary to realize the connection between PLC and host computer, it may be necessary to add switches and other equipment, and the specific configuration should be determined according to the actual needs.